Sample Risk Assessment & Method Statement

A fictional example showing the output Risk & Method produces for a small roof tiling job. All company, client, address and personal details below are fictional and shown for demonstration only.

Competent review required. Suggested risks, controls, method steps and COSHH prompts are general prompts only. They must be reviewed and adapted by a competent person for the actual site, task, workforce, equipment, substances and current guidance before use on site.

Risk Assessment & Method Statement

Sample — Pitched roof tile replacement

Ref: SAMPLE-RAMS-001 · Rev 1 · Prepared 1970-01-01

1. Project details

Company
Sample Contractors Ltd (fictional)
Client
Sample Client (fictional)
Principal contractor
Sample Main Contractor Ltd (fictional)
Site address
1 Sample Street, Sampleton SP1 1AA (fictional address)
Assessor
A. Sample (IOSH) — Site Supervisor
Site supervisor
A. Sample
Assessment date
1970-01-01
Review date
1970-01-31

Scope of works. Strip and replace approximately 12m² of damaged pitched roof tiles on a 2-storey domestic property using scaffold access. Includes tile removal, batten and felt check, and re-bedding of ridge tiles. Fictional sample for demonstration only.

2. Hazards & residual risk (11)

HazardBeforeAfter

Fall from pitched / flat roof edge

Category: Working at Height · At risk: Workers, Contractors, Public

208

Fall from ladder during access

Category: Working at Height · At risk: Workers, Contractors, Public

123

Fall through fragile roof / skylight

Category: Working at Height · At risk: Workers, Contractors, Public

154

Falling objects (tools, tiles, debris) from access / work at height position

Category: Working at Height · At risk: Workers, Contractors, Public

166

Suspension trauma after fall arrest

Category: Working at Height · At risk: Workers, Contractors, Public

83

Wind loading on temporary structures

Category: Working at Height · At risk: Workers, Contractors, Public

123

Back injury lifting heavy loads (>20kg)

Category: Manual Handling · At risk: Workers, Contractors

124

Uneven / damaged ground surface

Category: Slips, Trips & Falls · At risk: Workers, Contractors

82

Example controls (from hazard 1)

  • Pre-fabricate components off-site to remove work at height
  • Edge protection: double guardrail + toeboard (TG20:21)
  • Independent / tube-and-fitting scaffold by CISRS scaffolder
  • Debris netting + brick guards on scaffold
  • Scaffold inspection after assembly & at least every 7 days (WAH Regs)

3. Method statement (9 steps)

  1. Step 1 · Site set-up & access

    Site arrival, induction & RAMS briefing

    All operatives report to site, sign in, complete site-specific induction and read/sign this RAMS. Confirm welfare, first aid arrangements and emergency assembly point.

    Equipment: Sign-in sheet, RAMS, induction pack

  2. Step 2 · Inspection checkpoint

    Work area inspection

    Supervisor inspects the work area for new hazards (services, overhead lines, public, weather, ground conditions). Brief any changes to the team.

    Equipment: Inspection checklist

  3. Step 3 · Site set-up & access

    Exclusion zone & signage set-up

    Erect Heras fencing / barriers to segregate the work area from the public and other trades. Install warning signage and ensure pedestrian routes are clear.

    Equipment: Heras panels, signage, cones, tape

  4. Step 4 · Plant & equipment check

    Plant, tools & equipment pre-use checks

    Daily pre-use inspection of all plant, power tools and access equipment. Check certificates, PAT labels, scafftags and operator competence cards.

    Equipment: Pre-use checklist, scafftag, PAT records

  5. Step 5 · Sequence of work

    Carry out works in sequence

    Carry out the works in the order set out below. Apply all control measures from the risk assessment. Stop work and report immediately if conditions change or a new hazard appears.

    Equipment: Task-specific tools & materials

  6. Step 6 · Sequence of work

    Housekeeping & waste removal

    Maintain tidy walkways throughout the day. Remove waste to skips, sweep work area, store materials clear of access routes. Combustible waste removed daily.

    Equipment: Brooms, waste sacks, skip

  7. Step 7 · Inspection checkpoint

    Inspection / quality check

    Supervisor or third party inspects completed works against specification. Hold point — do not progress until signed off.

    Equipment: Quality checklist

  8. Step 8 · Emergency procedure

    Emergency procedure & first response

    In the event of injury, fire, structural collapse, services strike or other emergency: stop work, make the area safe if it is safe to do so, raise the alarm, call 999 where required, contact the site-specific emergency number where provided, notify the Site Supervisor / Principal Contractor and apply first aid. Casualty taken to the nearest A&E. Notify HSE under RIDDOR if required.

    Equipment: First aid kit, fire extinguisher, mobile phone

  9. Step 9 · Demobilisation / site clear

    Demobilisation & site clear

    Remove all plant, equipment and waste. Final walk-round with client / Principal Contractor. Reinstate any disturbed surfaces. Sign out.

    Equipment: Cleaning equipment

4. PPE

Hard hat (EN 397)Hi-vis (EN ISO 20471)Safety boots (EN ISO 20345)Gloves (EN 388)Full-body harness (EN 361) — anchoredEye protection (EN 166)

5. Permits & training

Permits required

  • Working at height permit (internal)
  • Scaffold handover certificate

Training & competence

  • CSCS / CISRS where appropriate
  • Working at height awareness
  • Manual handling refresher

6. COSHH prompts

No hazardous substances selected for this fictional sample. In a real RAMS, add any solvents, mortars, sealants, fuels or treatments used on site and attach the product Safety Data Sheets. Use the actual product SDS for product-specific hazards, PPE, first aid, storage and disposal. This library provides general prompts only and must be reviewed by a competent person.

7. Emergency arrangements

Emergency number (life-threatening)
999
Site emergency number
07700 900000 (sample)
First aider
A. Sample (first aid trained)
First-aid box location
Site cabin — east entrance
Fire assembly point
Front gate — far side of car park
Nearest hospital
Sample General Hospital, Sampleton (fictional)

8. Main Contractor Review

Space for the principal/main contractor to record review, feedback and acceptance of this RAMS before work starts on site. The full export includes signature blocks for the assessor, supervisor and each operative briefed.

Fictional sample generated by Risk & Method. Not a real project. Review and adapt every section with a competent person before use on site.